Cubico Sustainable Investments has lodged a 3,429-page submission for the Marmadua wind and battery project in Queensland, reducing the turbine count to 100. The package includes nearly $400 million in community payments over 35 years, though no decision timeline has been provided.
Gujarat Urja Vikas Nigam Limited has opened Phase XII of its wind power procurement, inviting bids for 250 MW of grid-connected capacity with an option to add another 250 MW. The tender requires developers to build transmission infrastructure and secure equipment from the ministry's approved list.
The Independent Planning Commission has granted final approval for the 1,400 MW Baldon wind project in southern NSW, which includes 200 MW of battery storage. The decision follows a planning process that included 73 objections and new conditions regarding traffic and environmental management.
Peoria County, Illinois, has approved the 500-megawatt Four Creeks wind farm, a $1.5 billion project by Repsol Renewables, following a 12-5 vote. The development includes 113 turbines on 27,000 acres and is expected to generate significant local tax revenue over its lifespan.
The 704-mW Revolution Wind project near Connecticut and Rhode Island has reached full commercial operations, becoming the third utility-scale offshore wind farm in the US. The $6.2 billion project powers over 350,000 homes after overcoming multiple stop-work orders and legal challenges.
Nabrawind’s Nabralift system, which eliminates the need for crawler cranes, is being tested at scale in Western Australia. The single-source nature of the technology raises questions about its viability for independent wind developers.
The Ministry of Climate, Energy and Environment has launched a 2.2 GW offshore wind tender covering the second half of 2026, bringing the total annual bidding volume to 4 GW. Price ceilings for both fixed and floating types have been reduced slightly from the first half of the year.
Fortescue is installing the first three 8 MW self-lifting Nabrawind towers at its 133 MW Nullagine wind project, part of more than 2 GW of wind and solar and 4 GWh of batteries for its Pilbara mines. Electric excavators, chargers and haul trucks are arriving ahead of a December push to decarbonise Flying Fish.
Bellevue Gold’s off-grid mine in Western Australia averaged a 75 per cent renewable energy share during winter, driven by a 51 MW wind and solar system. The facility ran 155 consecutive hours on 100 per cent renewables in May, supporting its claim as the world’s first net zero scope 1 and 2 emissions gold mine.
The floating wind sector is prioritizing international technical cooperation as U.S. developers face stalled negotiations and high heating fuel costs in Maine. Recent activities include testing shock-absorbing mooring systems and sharing steel platform designs to advance the technology toward a 15-gigawatt national target.
A trial at Macarthur wind farm found that laser-based wind forecasting significantly outperformed traditional methods in reducing regulatory costs. The study concluded that combining turbine and laser data offers the best path to minimizing financial penalties for inaccurate predictions.
Windlab, Altra Energy, Heron Energy and Neoen have proposed almost 13 GW of wind and solar capacity on pastoral land west of Whyalla, more than quadrupling South Australia’s grid-scale ambitions. The state says the early-stage projects could help power new industry in the Upper Spencer Gulf.
Lacour Energy has applied for approval to build a major wind and battery hybrid in Western Australia, with wind capacity ranging from 552 to 736 MW. The project includes a 500 MW battery system with up to eight hours of storage, aiming to support the state's transition away from coal.
The Victorian government has granted state approval to the Warracknabeal Energy Park, a 1.5GW wind and storage project in the Wimmera region. The development proceeds despite Coalition policies that would have blocked it via a 2km buffer zone.
Balranald Shire Council is urging night-time transport for oversized wind turbine components to protect caravan access to the town. The Baldon wind project in regional New South Wales involves 46 turbines with blades up to 90 metres long and tower sections significantly wider than local highway lanes.
Hydro Tasmania has refurbished the 2.5 MW Huxley Hill Wind Farm on King Island, extending its operational life by at least a decade. The project, led by Entura, involved repairing storm-damaged turbines and refurbishing nacelles in Denmark.
The Madhya Pradesh Electricity Regulatory Commission (MPERC) has adopted tariffs for 800 MW of wind projects, ranging from ₹3.98/kWh to ₹4.17/kWh. This move is expected to boost wind energy development in the state.