Clean energy news from India and beyondSubmit a story
Wind

Fortescue erects first self-lifting wind towers at Nullagine project

Fortescue is installing the first three 8 MW self-lifting Nabrawind towers at its 133 MW Nullagine wind project, part of more than 2 GW of wind and solar and 4 GWh of batteries for its Pilbara mines. Electric excavators, chargers and haul trucks are arriving ahead of a December push to decarbonise Flying Fish.

Luminity News Desk ·

AI-generated illustration: Fortescue erects first self-lifting wind towers at Nullagine project
Image: AI-generated illustration (Luminity / Workers AI)

Fortescue has begun erecting the first self-lifting wind towers at its 133 MW Nullagine wind project in Western Australia’s Pilbara, and expects its first electric haul trucks and other battery-powered mining equipment at its iron ore sites this year, RenewEconomy reports.

CEO Dino Otranto told an analyst briefing on the September quarter production report that installation of the first three 8 MW towers is well under way. “I was on site last weekend, where we’re well into installing the first three 8 MW Nabra wind towers, and they are an unbelievable sight to see,” Otranto stated.

Advertisement

RenewEconomy understands the tower sections are in place and ready to be lifted.

Tower Technology

The structural innovation driving this build comes from Nabrawind, a Spanish firm owned by Fortescue. The company designed the self-lifting tower system that defines the Nullagine project’s physical footprint. According to the company, the design does three things: it reaches better wind at greater height, it needs less concrete in the foundations, and it removes the need for the giant cranes normally used to lift turbine sections. The specific hardware deployed at Nullagine consists of 17 Envision turbines mounted on these Nabrawind towers. With a hub height of 210 metres and a tip height of 280 metres, they will be the tallest and most powerful turbines in Australia. Otranto also pointed to the site’s flat ground and consistent wind as an advantage.

Electric Machinery Deployment

  • 21 electric excavators are currently operating across Fortescue’s sites.
  • Six electric excavators at the Christmas Creek mine are outperforming their diesel counterparts.
  • The first 240 tonne electric haul truck is undergoing testing in Perth.
  • The first electric water carriers, graders and dozers have been delivered and will be readied for the Flying Fish and Eliwana mines.
  • Fortescue designed its own 6.4 MW fast chargers for heavy mining equipment, now in testing at its mine site.

The company says the Christmas Creek electric excavators are outperforming their diesel equivalents. The XCMG electric grader, dozer, loader and water cart arrived from China, and the first battery-electric haul truck is being built and tested in Perth. Otranto said in an earlier statement that all of this equipment will be brought together at Flying Fish in December.

Broader Renewable Buildout

The Nullagine wind towers sit within a much larger infrastructure program. Fortescue is currently constructing more than 2 gigawatts of combined wind and solar generation capacity, paired with 4 gigawatt hours of battery storage. The generation is meant to power Fortescue’s own mines and the hundreds of electric haul trucks and other equipment it plans to run there.

Construction of two large solar farms, at Turner River and Solomon Airport, is already under way.

Advertisement
Project Component Capacity / Status
Total Wind & Solar Over 2 GW under construction
Battery Storage 4 GWh
Solar Sites Turner River, Solomon Airport
Bonney Downs Wind Planned to exceed 800 MW total wind

Beyond Nullagine, Fortescue plans a bigger wind farm at Bonney Downs that would take its total wind capacity past 800 MW.

What to watch

The primary short-term objective centers on the December deadline at Flying Fish, slated to become Fortescue’s inaugural fully decarbonised mining operation. Otranto said the company will use it to “show what the future of mining can look like”.

Looking beyond internal operations, focus shifts to commercial growth. CEO Dino Otranto noted, "We’re in advanced discussions now with a number of third-party electron off-takers." Fortescue wants enough capacity beyond its own needs to offer a 200 MW renewable baseload supply to third parties, including data centres. Otranto said the attention data centres are getting is shining a light on regions such as the Pilbara and the midwest of Queensland as sources of abundant energy at costs that significantly undercut alternatives.

FortescueWind EnergyElectric TrucksSelf-Lifting TowersDecarbonisation

Source: RenewEconomy. This article is an original Luminity report based on the linked source.

Advertisement