Vikram Solar Q2 profit falls 70% as revenue declines 2.9%
Vikram Solar reported a 70% year-on-year drop in Q2 FY27 profit to ₹5.93 crore, with revenue declining 2.93% to ₹1,077.42 crore. The company secured 1.7 GW in new orders during the quarter, nearly doubling its Q1 intake.
Vikram Solar reported a 70% year-on-year decline in Q2 FY27 profit, which fell to ₹5.93 crore from ₹19.78 crore in the same period last year. This sharp drop in earnings coincided with a 2.93% decrease in revenue, which stood at ₹1,077.42 crore compared to ₹1,109.91 crore in Q2 FY26.
Vikram Solar secured 1.7 GW in new orders during Q2 FY27, more than double the 0.8 GW recorded in the preceding quarter, Q1 FY27.
Quarterly Financial Performance
Vikram Solar’s Q2 FY27 revenue fell 31.07% quarter-on-quarter to ₹1,077.42 crore from ₹1,563.09 crore in Q1 FY27. Profitability contracted even more sharply, with net profit dropping 95.38% sequentially to ₹5.93 crore from ₹128.49 crore in the previous quarter. Despite these declines in top-line and bottom-line figures, the company’s absolute EBITDA per watt improved by 37% compared to Q1 FY27.
First Half Consolidated Results
Vikram Solar reported consolidated revenue of ₹2,640.51 crore for the first half of FY27, reflecting a 17.70% year-on-year rise from the earlier figure of ₹2,243.48 crore. Net profit dropped 90.18% to ₹25.71 crore, down from ₹261.85 crore in the same period of the previous year. The company’s balance sheet showed relative stability, maintaining a net debt-to-equity ratio of 0.17x as of September 30, 2026.
Market Share and Distribution Growth
- Vikram Solar’s Q2 FY27 DCR (Distribution, Channel, and Retail) share rose to 22%, up from 7.5% in Q1 FY27.
- The company’s distribution and retail volume share increased to 44% in Q2 FY27, compared to 14% in the preceding quarter.
Manufacturing Expansion and Battery Subsidiary
In Gangaikondan, the firm is building a 9 GW N-type TOPCon cell plant, with initial output expected in December 2026. This location is also planned to accommodate a 9 GW ingot and wafer unit, with completion targeted for FY29.
Regarding energy storage, the company’s wholly owned subsidiary, VSL PowerHive, is constructing a BESS facility with an annual capacity of 7.5 GWh in Oragadam, Tamil Nadu. The plant’s inauguration is scheduled for January 2027, followed by the start of commercial operations in April 2027. The facility is scalable to 15 GWh in subsequent phases. VSL PowerHive intends to begin manufacturing 7.5 GWh of battery cells starting in 2028.
Order Composition and Module Specifications
The 1.7 GW in new Q2 FY27 orders spanned EPC, government, IPP, commercial and industrial, and mid-market customers. In a related development, Vikram Solar secured a 187 MW photovoltaic module supply order for projects in Karnataka and Tamil Nadu, as reported on 15 Oct 2026. That specific contract utilizes n-type TOPCon G12R modules featuring a glass-to-glass bifacial design intended to protect against moisture and mechanical stress. Separately, VSL PowerHive targets a total battery manufacturing capacity of 30 GWh by 2030 to support grid stabilization.
Source: Saur Energy. This article is an original Luminity report based on the linked source.