The Institute for Essential Services Reform estimates Indonesia’s solar capacity could reach 96.7 GW by 2029 if multiple deployment channels proceed simultaneously. This projection stands against a current installed base of just 1.59 GW, highlighting a significant gap between current status and government targets.

Luminity News Desk ·

AI-generated illustration: Indonesia could reach 96.7 GW solar by 2029, IESR estimates
Image: AI-generated illustration (Luminity / Workers AI)

The Institute for Essential Services Reform (IESR) estimates that Indonesia’s cumulative solar capacity could reach 96.7 GW by 2029, provided that multiple deployment channels proceed simultaneously. This modelled projection contrasts sharply with the current reality, where installed solar capacity stands at 1.59 GW as of the first quarter of 2026, according to IESR data.

The potential growth is set against a national target set by President Prabowo Subianto, who aims to achieve 100 GW of solar power by 2029.

Advertisement

Current capacity breakdown

  • Solar accounts for 1.5% of Indonesia’s power generation capacity as of Q1 2026, according to IESR.
  • Solar contributes only 0.3% to electricity production in the same period.
  • Rooftop PV represents the largest segment at 0.9 GW.
  • Utility-scale solar capacity stands at 0.33 GW.
  • Captive solar installations total 0.3 GW.
  • Remote area solar capacity is 0.06 GW.

The country crossed the 1 GW solar milestone in 2025.

Procurement and market potential

IESR outlines three separate pathways to achieve the 96.7 GW objective. The initial route comprises 8 GW of scheduled capacity from RUPTL and Mentari GigaOne tenders. The second pathway covers 56 GW of prospective capacity through PLN acquisitions. The final pathway, amounting to 33 GW, depends on distributed, rooftop, rural, captive, and diesel substitution projects.

The government’s 100 GW initiative, initiated in August, presently features 14 projects aggregating 5.2 GW. Nevertheless, IESR observes that specific completion timelines are established for just 526 MW of this total. Fabby Tumiwa, IESR’s CEO, stated that these acquisitions might serve as a market foundation for the solar supply chain, provided they are supported by steady policy and project assurance.

Suroso Isnandar was named the new president director of PT PLN to manage the technical and administrative consolidation of new capacity, effective 19 Oct 2026, according to an earlier report.

Supply chain and trade barriers

Indonesia’s domestic solar manufacturing base has expanded significantly, with IESR estimating module production capacity at 27 GW per year and cell capacity at 14.3 GW in 2026. IESR notes that more than half of the module capacity requires verification due to allegations of relabelling, a practice that can obscure the true origin of materials and complicate compliance with international trade standards.

Advertisement

US preliminary duties on Indonesian solar imports reached 104% in February 2026, rising to as high as 268% in final duties announced in September. Exports to the US plummeted 98%, falling from 2.2 GW in November 2025 to just 34 MW in April 2026, according to IESR data.

Systemic constraints and infrastructure

IESR points to regulatory voids, unclear procurement rules, and restricted grid connectivity as the main obstacles slowing solar rollouts across Indonesia. According to the institute, a high-electrification pathway anticipates a 160 TWh surge in demand by 2035 relative to business-as-usual, but the necessary physical infrastructure to handle this transition is still unfinished. Notably, the transmission lines needed to integrate solar power are not expected to be completed until the 2030-2034 window.

Although the RUPTL 2025-2034 plan allocates 42.6 GW for renewable energy and 10.3 GW for energy storage, IESR CEO Fabby Tumiwa remarked that progress is "far behind the government’s ambition to make solar power one of the backbones of the national energy system." This discrepancy between scheduled generation capacity and existing transmission capability forms a structural bottleneck. Luminity reported on 19 Oct 2026 that President Prabowo Subianto directed a full-scale reform of state utility PT PLN to speed up renewable energy infrastructure rollout, tackling these administrative and technical lags.