Aurora Energy Research: 80% of India's transmission lines delayed 15+ months
Aurora Energy Research reports that cumulative slippage on 80% of Indian transmission lines exceeds 15 months, coinciding with a rise in renewable curtailment to 2.7 TWh monthly. Developers face a structural mismatch as solar plants reach commissioning in 1.5 years while transmission lines take 3 to 5 years to build.
Aurora Energy Research indicates that India's monthly renewable energy curtailment hit 2.7 TWh as of May 2026. The company observes that this volume marks a dramatic rise from figures near zero at the beginning of 2025.
Per the report, the Indian grid incorporated more than 44 GW of new solar capacity during the twelve months preceding March 2026.
The Mismatch
When developers submit a bid, they lock in a tariff for 25 years. Solar projects typically move from financial close to commissioning within one to 1.5 years. In contrast, transmission lines require three to five years to complete.
The firm reports that cumulative slippage on roughly 80 per cent of lines exceeds 15 months. This delay is not uniform across the map; on the ten most significant corridors, slippage ranges between 15 and 30 months. These extended timelines are partly attributable to the bureaucratic process of securing forest clearances for Stage 1 and Stage 2 projects, which can take between 12 and 47 months.
Regional Bottlenecks
- In Rajasthan, 7 GW of installed capacity is currently operating under temporary general network access provisions.
- Similarly, 8.3 GW of capacity in Gujarat remains dependent on this interim arrangement.
- Solar-exclusive facilities in Rajasthan experience curtailment rates reaching up to 90 per cent during peak midday hours.
- Power output within the state is often reduced to zero from 11 a.m. through 2 p.m.
- Compensation for right-of-way is calculated at 85 per cent of the land's value specifically for tower footings.
Case Study: Khetri-Narela
Originally scheduled for energisation in November 2023, the line did not become operational until December 2025. Over a 25-month period, the project’s completion deadline was shifted 12 times.
The delays have left 4.5 GW of renewable capacity in the state unable to transmit power. Consequently, developers associated with the Khetri-Narela line lost around 60 per cent of their generation over two years.
While tower footings receive 85 per cent of the land value, the stringing corridors—the vast areas required for the overhead wires—receive only 15 per cent of the land value. This disparity highlights the complex negotiations developers and utilities face when securing the extensive land rights needed to complete the physical infrastructure that remains behind the nation’s solar expansion.
Transmission Reporting Flaws and Site Selection
Aurora Energy Research highlights four specific characteristics that make official transmission timelines untrustworthy. Initially, postponements occur in small steps, compelling developers to manage numerous minor, unforeseen adjustments instead of getting a viable schedule. Secondly, progress at the scheme level is presented as a total, obscuring whether a particular substation, line segment, or switchyard bay is causing delays across the whole evacuation path. Thirdly, reported completion rates are deceptive since towers are erected more quickly than conductors; a line may show 80 per cent tower completion yet remain years away from transmitting electricity. Finally, forest clearances follow erratic schedules, with official documents typically concealing which specific approval is stalled.
The study observes that Right of Way negotiations with landowners and felling permits from local bodies are managed separately. Regarding location choice, two interconnection sites 100 km apart can pose varying risks because the associated transmission lines will finish in different years. Aurora’s released data on headroom for 191 Rajasthan substations reflects capacity free from curtailment risk, not the limits specified in connection contracts. This information reveals how much additional capacity can be linked without triggering curtailment, enabling developers to evaluate concrete figures rather than depend on guesses. Time consumed by provisional grid connections results in lost output, a cost developers need to include in their bidding prices.
What to watch
Aurora Energy Research provides curtailment forecasts extending through 2032, offering a long-term view of potential grid stress as renewable capacity continues to outpace transmission build-out. However, no timeline has been established for when the necessary transmission upgrades and storage infrastructure will be constructed. This absence of a concrete schedule leaves the duration of current bottlenecks uncertain, making the firm’s projections a key indicator for assessing future revenue risks for developers reliant on timely grid access.