SECI issues BESS empanelment tender with four capacity tiers
The Solar Energy Corporation of India has launched a rolling empanelment process for battery energy storage system suppliers, integrators, and aggregators. The tender establishes four capacity tiers with specific financial and technical criteria, with bids due by November 30, 2026.
The Solar Energy Corporation of India (SECI) has released a call for empanelment targeting battery energy storage system (BESS) suppliers, integrators, and aggregators. This program utilizes a two-stage procurement mechanism within a rolling empanelment framework.
Per the tender specifications, bidders are required to submit their proposals by November 30, 2026.
Procurement Structure
The empanelment process operates through a two-phase framework. Phase one serves as an open, continuous qualification round where suppliers must meet specific technical and financial benchmarks. Upon successful empanelment, these organizations become eligible for phase two, which comprises project-specific acquisitions executed via Requests for Quotation and electronic reverse auctions.
In phase two initiatives, the scope of work encompasses the design, engineering, manufacturing, supply, installation, testing, and commissioning of the BESS. SECI or the associated project entity handles the procurement of balance of plant and civil works independently. On 1 October 2026, Luminity noted that participants in the 800 MW/3,200 MWh standalone BESS tender have the option to bid anywhere from 50 MW/200 MWh up to the total capacity, with the deadline for online bid submission set for 30 October 2026.
Capacity Tiers and Requirements
SECI has segmented the empanelment into four capacity tiers to match vendor capabilities with project scales. A vendor qualifying for a higher tier automatically becomes eligible for all lower tiers.
| Tier | Capacity Range | Cumulative Technical Requirement |
|---|---|---|
| I | Up to 100 MWh | 10 MWh |
| II | >100 MWh to 300 MWh | 30 MWh |
| III | >300 MWh to 600 MWh | 60 MWh |
| IV | >600 MWh to 1,000 MWh | 100 MWh |
Vendors can qualify through two distinct technical routes. Route I is reserved for entities engaged in battery manufacturing and supply that possess an operational facility. Route II covers integrators, suppliers, or aggregators of grid-interactive BESS.
Financial and Administrative Terms
- Validity: Empanelment is valid for one year.
- Defects: A 12-month defect liability period applies from the date of material delivery.
- Bid Fee: A non-refundable bid processing fee of Rs 5,000 plus GST is required.
- Deposit: No earnest money deposit is required at the empanelment stage.
- Payment Timeline: The empanelment fee and bank guarantee are due within 15 days of notification.
- Financial Criteria: Applicants must demonstrate a positive net worth in the last financial year.
| Tier | Empanelment Fee | Bank Guarantee | Annual Turnover | Working Capital |
|---|---|---|---|---|
| I | Rs 25,000 | Rs 18.6 million | Rs 279 million | Rs 232.5 million |
| II | Rs 50,000 | Rs 55.8 million | Rs 837 million | Rs 697.5 million |
| III | Rs 75,000 | Rs 18.6 million | Rs 1,674 million | Rs 1,395 million |
| IV | Rs 100,000 | Rs 186 million | Rs 2,790 million | Rs 2,325 million |
Stage-II Scope and Guarantee Validity
Stage-II agreements obligate vendors to supply BESS DC blocks, battery management systems, power conditioning systems, thermal management systems, fire suppression systems, and energy management systems, in addition to required spare parts and a complete warranty. The detailed commissioning schedules and project-specific maintenance duties will be defined in the individual Stage-II RfQs. The empanelment bank guarantee, which functions as the earnest money deposit for Stage-II, must remain valid for 15 months.
Source: Renewable Watch. This article is an original Luminity report based on the linked source.