Torrent Power says 3,000-MW Karjat pumped storage project lies outside Bhimashankar sanctuary
Torrent Power says its 3,000-MW Karjat pumped storage project in Maharashtra lies about 16 km from the Bhimashankar Wildlife Sanctuary, outside its eco-sensitive zone, after receiving environmental and forest clearances. The company estimates the 80-year project will avoid 5.85 million tonnes of CO2 a year.
Torrent Power has defended its proposed 3,000-MW pumped storage project at Karjat in Maharashtra's Raigad district against environmental concerns, saying the site is about 16 km from the Bhimashankar Wildlife Sanctuary and that all project components fall outside the sanctuary and its eco-sensitive zone. The company also rejected reports of tree felling inside the sanctuary as based on incorrect information.
Pumped storage plants pump water to an upper reservoir when surplus power, typically solar and wind, is available, and release it to generate when demand rises. Torrent says the project will supply Maharashtra and cut reliance on coal-fired power in the evening peak.
Regulatory Path and Site Details
Torrent Power navigated a clearance process spanning approximately 18 months, engaging statutory bodies including the Expert Appraisal Committee and the Forest Advisory Committee. The project carries an operational life of up to 80 years, a longevity that distinguishes pumped storage from many other grid assets. The facility requires 233 hectares of forest land, a footprint that is 52 times lower than that of conventional hydropower projects of comparable capacity. The project location sits 16 km from the Bhimashankar Wildlife Sanctuary.
Environmental Impact and Mitigation
- Compensatory afforestation land: 253 hectares
- Trees to be planted across green belt, muck-disposal site and other areas: 60,000
- Trees to be planted on compensatory land: 30,000
- Existing trees on compensatory land: 70,000
- CO2 offset time for felled trees: 10 days of operation
- Project status: Received Environmental Clearance, Forest Clearance, and Forest Diversion Order
Torrent Power has secured the Environmental Clearance, Forest Clearance, and Forest Diversion Order, completing the regulatory requirements for site preparation. The developer plans about 60,000 trees across the green belt, muck-disposal site and other project areas, and a further 30,000 on 253 hectares of private land it has handed to the Forest Department for compensatory afforestation. This compensatory area currently supports 70,000 existing trees, providing a baseline for the ecological management of the diverted forest resources.
The carbon dioxide offset for the trees removed during construction is equivalent to just 10 days of the facility’s operation.
Energy Output and Emission Reductions
Torrent estimates the facility will supply about 6,570 million units of electricity a year, enough to meet the evening power needs of around 5.5 million homes. By displacing coal-based generation, it says the plant will reduce annual coal consumption by 4.33 million tonnes. This shift prevents 5.85 million tonnes of CO2 emissions each year, amounting to 468 million tonnes of avoided emissions over the project’s 80-year operational life.
Annual reductions include 36,800 tonnes of sulfur dioxide, 10,600 tonnes of nitrogen oxides, and 1,200 tonnes of particulate matter. The plant also prevents the release of 0.66 tonnes of mercury per year.
The company also estimates savings of 19.7 billion litres of cooling water a year. It also eliminates the production of 1.64 million tonnes of fly ash and reduces the need for open-cast mining by 40 hectares per year.
| Metric | Annual Value |
|---|---|
| Electricity Supply | 6,570 million units |
| Homes served (evening needs) | 5.5 million |
| Coal Reduction | 4.33 million tonnes |
| CO2 Emissions Prevented | 5.85 million tonnes |
| SO2 Reduction | 36,800 tonnes |
| NOx Reduction | 10,600 tonnes |
| Particulate Matter Reduction | 1,200 tonnes |
| Mercury Reduction | 0.66 tonnes |
| Cooling Water Saved | 19.7 billion litres |
| Fly Ash Reduction | 1.64 million tonnes |
| Open-Cast Mining Reduction | 40 hectares |
Construction Footprint and Water Management
Torrent Power states the project will store water that would otherwise flow downstream towards the sea, operating in a manner complementary to the river system. The company asserts that the carbon benefits of the facility outweigh the emissions associated with trees felled for construction, noting that the latter are offset in about 10 days of operation.
Sanctuary and temple concerns
Torrent Power says every element of the scheme is situated beyond the sanctuary boundaries and its designated eco-sensitive area. The firm further highlighted that no construction activities are planned in the vicinity of the Bhimashankar Jyotirlinga temple. Mitigation includes a wildlife conservation plan, catchment-area treatment, compensatory afforestation and long-term habitat management. Over the project's life, Torrent says, the benefit is about 3,000 times the loss.
Source: ETEnergyWorld Renewables. This article is an original Luminity report based on the linked source.
